How Long Does it Take to Remodel a Bathroom in 2024?

Rebecca Denis
Rebecca Denis
Head of Design
Sep 4, 2023
How Long Does it Take to Remodel a Bathroom in 2024?

Home transformations can be a great way to breathe new life into a living space. But while home improvement TV shows can make the process seem like anyone can do it, tackling a remodel on your own without any prior knowledge or experience can be a challenge.‍ Bathroom renovations are particularly unique. Unlike other rooms in the house, bathrooms have specific plumbing and electrical needs to navigate. And given that a bathroom is among the most frequently used spaces in a home, careful planning becomes essential.‍ At Revive, we're no strangers to the unique requirements of a bathroom remodel. Whether looking to just do some small feature upgrades or a full-scale renovation, we've seen it all and have some important tips and best practices you should follow to complete your remodel safely, on time, and within budget.

Understanding the Bathroom Remodel Timeline

Whether you're updating your kitchen, bathroom, or the whole house, it's important to gauge a realistic timeline for your renovation. This ensures you can plan out your steps and also set clear expectations as the project progresses.

The simplicity or complexity of your design plans will primarily drive your bathroom remodel timeline. A well-constructed design plan should include:

  • A completed layout of your new bathroom design concept
  • The types of fixtures you'll be using and their location
  • Any tile or flooring you'll be installing
  • Paint colors or wallpaper type

Although there might be additional design features you'd like to incorporate, the above bullet list should give you a good start. Determining how these elements come together ahead of time can provide a clearer vision for the final outcome of your project.

With your remodel roadmap in place, you'll now need to factor in different phases of the project that will all impact how long your project will take. These phases will include:

  1. Initial Design Phase: During this phase, you'll sit down with your contractor or designer to go over your vision. Together, you'll make adjustments if needed and determine the exact approach for the project.
  2. Planning Phase: After locking in the design, the next step is strategizing its execution. This means choosing materials, picking the right subcontractors, and mapping out the timeline for completion.
  3. Preparation Phase: This phase involves readying your home and the bathroom for the remodel. It could involve clearing the space, setting up a temporary bathroom, and ensuring all necessary materials and tools are on hand.

Once the preliminary steps are finished, you can kick off the construction phase. Bear in mind that a typical bathroom renovation lasts around 4 to 6 weeks, provided no unforeseen challenges pop up. Still, it's wise to prepare for potential hiccups and allow some wiggle room in your timeline.

Pre-Construction Phase

Many assume that the bulk of time in a bathroom remodel is consumed by the actual building work. However, the pre-construction period can be just as time-consuming. There are several critical steps to finalize before any construction begins.

Design and Budget Considerations

Figuring out a realistic budget at the start of a remodeling project can be tricky. Given the diverse range of design options, homeowners often struggle to estimate the real costs and how to balance their desired features without overshooting the budget.

Working with a designer or contractor at this stage can be beneficial. Their expertise in different design choices and their associated costs can help in creating a budget that accommodates your needs.

Permits and Documentation

It's a misconception that interior renovations don't require official documentation or permits. In many scenarios, local authorities mandate homeowners to secure permits for specific remodeling projects.

For example, if you're making structural modifications or additions, more than likely, you'll need building permits. Some areas also have stringent rules for updating or replacing electrical or plumbing systems. Doing your homework on these scenarios in advance can save you from unnecessary setbacks and expenses.

Setting Priorities and Deciding On DIY Tasks

Although bathrooms aren't typically large spaces, there is a lot of benefit to carefully planning what priorities should be tackled first. You may need to have contractors or specialists come in for certain tasks, such as plumbing or electrical work.

However, you can also identify certain tasks that you may be able to take on yourself, such as painting or installing fixtures. Even electing to handle the cleanup work yourself can save you money in the long run.

Construction Phase

After wrapping up the pre-construction phase, you'll transition to construction work. The scope and processes involved in this phase will vary based on the extent of your bathroom renovation, which could include any number of the following steps:

Demolition

If you're redoing plumbing, installing a bathtub or fixtures, or expanding the room, then demolition will be the first process you complete. This will be messy and loud, so it's important to plan ahead and communicate with your neighbors if necessary. Make sure you have a designated area for debris and proper disposal methods in place.

Rough-In Installation

Rough-in refers to the installation of all plumbing and electrical systems that will be hidden behind the walls, floors, and ceilings. This should be done before any walls are closed up, and it's a good idea to have a licensed professional handle this step for safety.

Inspections

Before you install insulation or drywall, it's important to have all plumbing and electrical work inspected. This ensures all installations meet the required standards and prevents potential problems down the line. It's a good idea to arrange these inspections ahead of time to keep the construction timeline on track.

Drywall Repair and Painting

After inspections have been passed, you'll be ready to start hanging drywall and getting the space ready for painting or wallpapering. While you can wait to paint the bathroom once everything is finished, sometimes it's easier to paint before all the fixtures are in place. This avoids any potential drips or brush marks on new fixtures or flooring.

Flooring and Fixture Installation

Once the walls are complete, it's time for flooring installation. This is usually done before installing fixtures to avoid damaging them during the process. Once the flooring is in, you can begin installing your new vanity, bathtub/shower, toilet, and other fixtures.

Post-Construction Phase

Once the major work of the construction is completed, you'll enter the wrap-up stage.

This phase is all about perfecting the details. It might involve some last-minute painting, adding fixtures like towel holders or mirrors, or putting in some decorative touches. At this point, it's essential to ensure every task meets your standards.

After everything is in place, schedule a walkthrough with your contractor. This lets you both assess the finished project, address any lingering issues, and verify that everything aligns with your initial vision.

Factors Affecting Bathroom Remodel Time

Even if you've taken the time to plan your remodel to a tee, there may still be factors that can affect the timeline. These could include unforeseen issues or delays in getting the necessary materials.

Below are some common factors that can impact the time it takes to complete a bathroom remodel:

Cosmetic vs. Complete Rebuild

The extent of your remodel is one of the most significant factors affecting the timeline. A simple cosmetic update - like repainting walls, replacing fixtures, or installing new tiles - can often be completed in a few days to a week. On the other hand, a complete rebuild involving structural changes and new installations can take several weeks to months to complete.

DIY vs. Hiring a Contractor

Your decision to undertake the renovation yourself or bring in a contractor can also influence the project's duration. While going the DIY route might be cost-effective, it can extend the timeline. This is especially true if you're picking up new skills along the way or if you're restricted to working during your spare hours.

A professional contractor has the necessary expertise and resources to complete the project efficiently. However, they may also have a backlog of projects or unexpected delays that can affect the timeline.

Availability of Materials and Shipping Delays

Your renovation timeline can be dynamic depending on the availability of the materials you've selected. While commonly used materials are usually on hand, unique or custom items might come with an extended waiting period.

To avoid any holdups, it's wise to secure your materials early in the process and ensure they're readily available before the building phase kicks off. Even though it's always a possibility that your remodel ends up requiring elements you didn't plan for, having the majority of your materials on hand can help keep the project on track.

Labor Shortages and Permit Delays

Unexpected issues such as labor shortages, design changes, and permitting delays can also extend the remodel time. Labor shortages can slow down progress, while making design changes mid-project can lead to repeated work.

Additionally, obtaining permits can sometimes take longer than anticipated, particularly if revisions to your plans are required. This often leads many people to try and shortcut this process, which can be a major problem. Not only can avoiding necessary permits be dangerous if there becomes a safety issue, but it can also make selling your home more challenging down the road.

Tips and Recommendations

Keep in mind that while renovation work can be demanding on time and resources, following certain tips and guidelines can help mitigate setbacks and guarantee a more streamlined process overall.

Importance of an Organized Approach

Organization is key to a successful remodel. Keep all your plans, contracts, receipts, and other important documents organized and easily accessible. This will ensure better communication and prevent misunderstandings.

Having a clear budget in mind is also crucial. Be upfront about your budgetary requirements with your contractor from the start, and keep track of all expenses to avoid overspending. Remember to account for unexpected costs that may arise as well, as most remodel projects end up introducing some additional costs that weren't initially planned for.

When you have your design plans finalized, ordering materials early in the process is encouraged. Delays in material delivery can significantly slow down the project. By having everything on hand before construction begins, you can help keep your project on schedule.

Engage Actively During the Construction Phase

Your level of participation in a project shouldn’t taper off once the construction begins. Even if you're not hands-on with the work, maintaining an active presence is crucial. Always be reachable for any questions or discussions, and address concerns with your contractor right away.

Frequent check-ins on the site can keep you aware of how things are looking and confirm that everything looks the way you want it.

Make Timely Payments and Avoid Making Unnecessary Changes

Paying your invoices on time not only builds goodwill with your contractor but also helps to ensure a streamlined construction process. Address any minor hiccups or concerns right away, and avoid using payment as leverage.

A strong, professional rapport with your contractor is important for your project's success. By being consistent with your financial commitments and avoiding too many unplanned changes, you can avoid potential disputes or delays in the timeline.

Set Clear Expectations and Partner with Experienced Professionals

Before work begins, set clear expectations with your contractor regarding the project timeline, cost, and desired results. A good contractor will appreciate your clarity and strive to meet your expectations.

A major key to your project's success is collaborating with highly qualified and trustworthy professionals. Invest time in researching potential designers and contractors who are known for their quality work and ability to stay within the budget. Look for recommendations, read reviews, and ask detailed questions to ensure you're trusting the success of your remodel with the right people.

What to Expect When Remodeling a Bathroom

It’s important to know what to expect. Anticipate a journey of choices and challenges. Remodeling a bathroom typically involves decisions about layout, fixtures, and aesthetics, along with the nuts and bolts of plumbing and electrical work. It’s a balance between design dreams and practical considerations. Preparation is key—knowing your budget, understanding the scope, and perhaps most importantly, being ready for the unexpected.

What are the Most Common Bathroom Renovations

Bathrooms may be compact, but the possibilities for upgrades are vast:

  1. Fixture Upgrades
  • Faucets and Showerheads: Swapping out old, inefficient models for sleek, water-saving designs not only refreshes the look but also conserves resources.
  • Toilets: Modern toilets offer improved functionality and reduced water usage, making them a smart choice for eco-conscious homeowners.
  1. Vanity and Countertop Overhauls
  • Replacing the vanity can transform the entire vibe of the room. Options range from bespoke cabinetry to stylish, off-the-shelf units, topped off with durable and chic materials like quartz or marble.
  1. Tile Revamps
  • Whether it’s the floor or the walls, new tiles can inject life into a dated bathroom. Homeowners often opt for contemporary styles, colors, and textures to give the space a modern feel.
  1. Lighting Enhancements
  • Upgrading lighting fixtures can brighten and enlarge the perceived space. Many choose energy-efficient LEDs, add dimmers for mood lighting, or incorporate dramatic fixtures above the vanity.
  1. Shower Conversions
  • Ditching the old tub for a spacious walk-in shower is a common renovation, particularly in master baths. This often includes custom tile work and sleek glass doors to create a spa-like environment.
  1. Boosting Storage
  • To tackle clutter, adding smarter storage solutions like extra cabinets, open shelving, or recessed niches can be a game-changer.
  1. Accessibility Features
  • For long-term planning, installing safety features like grab bars, walk-in tubs, or zero-entry showers can make bathrooms safer and more accessible.
  1. Incorporating Smart Technology
  • For a touch of luxury, homeowners are integrating tech like smart mirrors that display news or weather, automated lighting systems, or even underfloor heating for added comfort.

How Long Does a Bathroom Remodeling Take if There Are Custom Features?

Thinking about taking on a bathroom remodel with custom features? The timeframe can vary significantly depending on the specifics of your project. Here’s what you might expect for different types of custom renovations:

Accessible Bathrooms 

Adapting a bathroom to be more accessible often involves installing features like walk-in tubs, grab bars, and broader doorways to accommodate easier access. If you're adding these types of elements, expect the project to span from three to six weeks, possibly longer if structural modifications are required to widen doorways or reconfigure spaces.

Smart Bathrooms 

Incorporating smart technology into your bathroom brings a futuristic touch but also adds complexity to the remodel. Fitting in smart mirrors, voice-controlled showers, and automated lighting involves integrating sophisticated systems into your existing plumbing and electrical frameworks. Such installations typically add a few weeks to your timeline, extending the total duration depending on how seamlessly these technologies mesh with your infrastructure.

Conversions and New Construction 

Turning a non-bathroom space into one, or building a new bathroom from the ground up, is an extensive undertaking. This kind of project not only demands thorough plumbing and electrical work but may also require significant structural changes. The timeframe for such a remodel can stretch from six weeks to several months. Key factors influencing this duration include the scale of the project, the efficiency of obtaining necessary permits, and the intricacy of the construction tasks.

How to void Issues With Your Remodel

Navigating a home remodel without hitting any roadblocks may sound near impossible, but with some strategic planning and smart practices, you can minimize problems and ensure a smoother renovation process. Here are key strategies we have found to help avoid issues during a remodel:

Thorough Planning

  • Start with a clear vision and detailed plans. Know exactly what you want before any work begins. Sketch out designs, choose materials, and finalize details upfront. This level of preparation helps prevent misunderstandings and last-minute changes that can cause delays and inflate costs.

Hire the Right Professionals

  • Choosing the right contractor is crucial. Look for professionals with strong reputations and relevant experience. Check their credentials, read reviews, and ask for references. A good contractor will help you navigate the complexities of the project, keep things on track, and handle any unforeseen issues that may arise.

Set a Realistic Budget

  • Ensure your budget accounts for all aspects of the remodel, including materials, labor, and a contingency fund for unexpected expenses (typically 10-20% of the total budget). Underestimating costs can lead to compromises and cut corners, which might affect the quality and outcome of your remodel.

Effective Communication

  • Maintain open lines of communication with your contractor and crew. Regular check-ins and being on-site as much as possible can help you stay informed of the progress and quickly address any issues that arise. Clear communication can also ensure that your vision stays consistent throughout the project.

Understand Permit Requirements

  • Before starting your remodel, understand the permitting requirements in your area. Ensuring all necessary permits are obtained can prevent legal issues and ensure your renovation complies with local building codes, which is essential for your safety and for future resale.

Prepare for the Unexpected

  • Even with the best plans, unexpected issues can arise—be it hidden problems like plumbing or electrical issues behind walls, or delays in material shipments. Flexibility and a contingency plan can help manage these surprises without major disruptions to your project.

Quality Control

  • Regularly inspect the work done by contractors and workers. Don’t hesitate to speak up if something doesn’t meet your expectations. Addressing issues quickly can prevent costly fixes after the project is completed.

Get The Most Out of Your Bathroom Remodel

A bathroom remodel is a project that can add significant value to a home when executed correctly. The key to a successful remodel lies in thorough planning, understanding potential challenges, and maintaining effective communication throughout the process. 

By keeping these factors in mind, you can navigate the remodeling process smoothly and enjoy a new bathroom that looks great and functions even better.

Frequently Asked Questions

Let’s dive into some frequently asked questions about bathroom remodeling.

How fast can you remodel a small bathroom?

  • Speedy renovations aren't just the stuff of TV magic; they're entirely possible with the right planning. For a small bathroom, if you’re focusing on cosmetic changes like new paint, fixtures, or even quick updates to tiling, the entire process could be wrapped up in as little as two to three weeks. Of course, this assumes decisions are made swiftly and there are no unexpected delays in getting materials or labor.

How long does it take to redo a shower?

  • Redoing a shower can be a simple swap or a complete redesign, influencing how long the project takes. If you're replacing existing features with new ones in the same layout, the job could be done within a week. However, if you're planning a more elaborate overhaul—say, expanding the shower area or installing advanced features like multiple shower heads or custom tiling—prepare for the work to extend up to three or four weeks, especially if any structural adjustments are needed.

What is the best time of year to remodel a bathroom?

  • Timing can impact your remodeling project significantly. Generally, winter and early spring are considered ideal times to undertake indoor renovations like bathroom remodels. Contractors often have more availability during these months, and you might even snag some off-season discounts on materials. Plus, undertaking renovations during cooler months means any out-of-home disruptions (like needing to turn off water during a freeze risk) are less bothersome.
Share this post
Rebecca Denis
Rebecca Denis
Head of Design
Sep 4, 2023

Rebecca Denis, Head of Design at Revive Real Estate, is an accomplished and highly creative interior designer with over ten years of experience in the industry.

Disclaimer: The information provided in this blog is for general informational purposes only and should not be considered financial, legal, or real estate advice. ROI estimates, cost ranges, and market trends are based on publicly available data and general industry insights and may not accurately reflect individual circumstances, regional specifics, or current market conditions. Revive makes no guarantees regarding outcomes or returns on investment. Readers are strongly encouraged to consult with licensed professionals, such as contractors, real estate agents, or financial advisors, to assess their unique needs and conditions before starting any remodeling or home improvement projects. Revive is not liable for decisions made based on the information provided herein.

Unlocking equity is hard,
we've got your back.

See what's possible, it's your real estate.

Discuss home